With the Static Scheduler, users can set up schedule-based limits which override the prevalent limit currently advising the load manager.
Static schedules can be set up for:
- the whole site, in the Load Management configuration
- on a specific charging cluster, in the Cluster configuration
- on an individual charger, in the Charger configuration
Which limit does the schedule “override”?
The schedule will be applied to the lowest limit currently applied on the site, the cluster or the charger.
Does the functionality differ between Static Load Management and Dynamic Load Management?
No
How can I use the static scheduler in combination with solar excess to charge my vehicles?
Prerequisite
The solar system needs to be installed in the same electrical distribution as the chargers.
- Install a power meter on the supply cable of the solar system to monitor the production.
- Connect the power meter to HARMON-E
- Configure the power meter in HARMON-E
Configuration
Use Case: Solar
Position: Direct
Set to Load Management: On
Choose the charging cluster in which to optimise
What to expect?
If you set the schedule to 0 A and the solar reports -50 A then there will be 50 A available for charging within the cluster and the load manager will allocate charge currents accordingly.